2004 Projects from the Reserve For Repairs and Renovaton (2004 R&R) Printable Version PDF List
Year Building Project Category Project Title Project Budget Project Designer Planning Manager Project Resource & FCAP Contact Status (update March 21, 2006)
Roof Repairs and Replacements  
2004 Koury Natatorium Roof Replacement Replace EPDM roof 470,000 Rooftop Systems Engineers Masaya Konishi Geoffrey Lee Estimated construction completion August 2006
2004 Dean Smith Center Roof Replacement Coverage of the upper area of the EPDM roofing by adjoining new teflon to existing dome 230,000 Rooftop Systems Engineers Masaya Konishi Geoffrey Lee Estimated construction completion August 2006
2004 Morehead Planetarium Roof Restoration Roof replacement (six roof sectors) 390,000   Paul Kapp Geoffrey Lee Construction documents phase
2004 Aycock Family Medicine Roof Replacement Roof Replacement (single ply EPDM roof sectors) 100,000   A&E Services Geoffrey Lee Completed
Structural Repairs  
2004 YMCA Structural Repairs Foundation water-proofing 100,000 Sigma Stewart Eng. Paul Kapp Geoffrey Lee Estimated construction completion January 2007
2004 Art Studio Building Structural Repairs Structural repairs for metal roof framing 150,000   A&E Services Geoffrey Lee Completed
2004 Dean Smith Center Structural Repairs Replace caulking on precast joints on the exterior of arena 120,000 Rooftop Systems Engineers Masaya Konishi Geoffrey Lee Estimated construction completion August 2006
Repairs to Electrical, Plumbing and Heating, Ventilating, and Air-Conditioning Systems  
2004 YMCA HVAC System Install central HVAC system 400,000 Sigma Stewart Eng. Paul Kapp Brad Davis Estimated construction completion January 2007
2004 YMCA Plumbing Replace plumbing 150,000 Sigma Stewart Eng. Paul Kapp Brad Davis Estimated construction completion January 2007
2004 YMCA Electrical Systems Upgrade lighting and electrical distribution system 200,000 Sigma Stewart Eng. Paul Kapp Joel Carlin Estimated construction completion January 2007
2004 208 West Franklin Street HVAC System Replace HVAC components (AHUs, condensing units & temperature control systems) 165,000 A&E Services David Shaffer Brad Davis Construction phase
2004 Mary Ellen Jones Building Elevator Systems Upgrade existing analog controls for elevators with digital systems 565,922 Donna D. Kramer, PE Bill McGraw Geoffrey Lee Estimated construction completion March 2007
2004 Hamilton Hall Elevator Systems Upgrade existing analog controls for elevators with digital systems 290,000   Jerry Guerrier Geoffrey Lee Construction phase
2004 Carmichael Auditorium, Hamilton Hall, FPG Child Dev. Center#1, Francis Owen Lab Electrical Systems Replace / install emergency generators and automatic transfer switches 185,000 A&E Services Stanley Young Joel Carlin Carmichael = Completed; FPG & Frances Owen = Construction phase; Hamilton = Combined with Existing Renovation Project (Estimated construction completion August 2007)
2004 Walter Davis Library HVAC System Advanced planning for HVAC replacement and fire protection addition 150,000 United Eng. / Pearce Brinkley Cease + Lee Diane Gillis Brad Davis Final report received January 2006
2004 Morehead Planetarium HVAC System Replace three AHUs and diffusers in Banquet Room to improve IAQ 130,000   Paul Kapp Brad Davis Project on hold
2004   Electrical Systems Emergency generator DOI electrical code analysis 60,000 A&E Services Facilities Services Joel Carlin 90% completed
Improvements to Meet Requirements of the Americans with Disabilities Act  
2004 Campus-wide ADA Continuation of campus-wide ADA program 500,000   Michael Pierce Geoffrey Lee Ongoing
2004 Thurston-Bowles Building ADA Renovate 3rd floor bathroom for ADA-compliance 125,000   Bill McGraw Geoffrey Lee Construction phase
Improvements to Meet Fire Safety Needs  
2004 YMCA Fire Sprinkler System Install fire sprinkler system 150,000 Sigma Stewart Eng. Paul Kapp Brad Davis Estimated construction completion January 2007
2004 Electrical Distribution Center, Nash Hall and Surplus Property Warehouse Fire Alarm System Install and upgrade fire alarm systems and advanced planning to network addressable fire alarm systems 125,000   A&E Services Joel Carlin Nash = Cancelled; Electrical Distribution Center & Surplus Warehouse = Construction phase
Improvements to Existing Facilities for Energy Efficiency  
2004 Ambulatory Care Center Interior Repair and replace automatic doors 60,000   A&E Services Geoffrey Lee Completed
2004 Thurston-Bowles Building Air Compressors Replace three existing 40HP lab air compressors with energy-efficient radial units 140,000 Dave Mercs A&E Services Brad Davis Completed
Improvements to Remove Asbestos, Lead Paint and Other Contaminants  
2004 Morehead Chemistry Labs, Giles F. Horney Bldg and Security Services Bldg Underground Fuel Tanks Remove three underground steel fuel tanks and replace with above-ground tanks 160,000   A&E Services Joel Carlin Construction phase
Improvements to Roads, Walks, Drives and Utilities Infrastructure  
2004   Infrastructural Improvements Repair and resurface Friday Center Drive 50,000   A&E Services Geoffrey Lee Completed